Burndown Chart in Excel: Build One in 6 Steps (2026)

By Priyendra Kumar (PK) · 19 November 2026

To make a burndown chart in Excel, list your sprint’s stories with their story points and the date each one was finished. Then build a small day table: for each working day, work out the ideal remaining points (a straight line from the total down to zero) and the actual remaining points (total scope minus a SUMIFS of points finished on or before that day). Select the Day, Ideal and Actual columns and insert a Line chart. Make the ideal line dashed grey and the actual line solid. That’s the whole method: four formulas and one chart, with no add-in or paid tool.

This tutorial comes from Module 11 (Agile and Kanban in Excel) of my Project Management in Excel course, the lesson “Burndown, burnup and velocity charts”. For this post I made new sample data for a fictional US online store team, Harbor Lane Outfitters, running a 10-day sprint. I built every formula and both charts in Microsoft 365 Excel for Windows (build 20527, November 2026), so the numbers and screenshots below came out of Excel itself.

Burndown chart in Excel showing the ideal remaining dashed line and the actual remaining story points line
The finished burndown chart: the team started slowly, absorbed a scope change on Day 4 and ended the sprint with 3 points left.

⬇️  Download the Free Practice File (ZIP)
Practice workbook + solution workbook with both charts · no sign-up

What a burndown chart shows (in one minute)

A burndown chart tracks how much work is left in a sprint, day by day. The horizontal axis is the sprint day. The vertical axis is the work remaining, usually in story points (hours work too). Two lines tell the story:

  • Ideal remaining: a straight line from the committed total on Day 0 down to zero on the last day. It is the pace you would need to finish on time.
  • Actual remaining: what really was left at the end of each day.

If the actual line sits above the ideal line, the team is behind. Below it, they are ahead. That is why stand-ups and sprint reviews use it: anyone can read it in five seconds.

The sample data: one sprint, 14 stories

Open the practice file and go to the Stories sheet. Each row is one user story with an owner, story points, the date it was added to the sprint and the date it was done. A blank Done Date means the story was not finished. Two details are there on purpose, because real sprints have them:

  • Story S-114, a 5-point payment bug, was added on Thursday, Nov 5, in the middle of the sprint. So the scope grows from 55 to 60 points.
  • Story S-112, a 3-point accessibility pass, never got finished.
Burndown chart in Excel practice data: sprint backlog table with story points, added date and done date
The Stories sheet, an Excel Table named tblStories.

Keep the data as an Excel Table (Ctrl+T). The formulas below use structured references like tblStories[Points], so when you add a story, every number and the chart update by themselves.

How to make a burndown chart in Excel, step by step

Step 1: Set up the sprint inputs

On the Burndown sheet, put three inputs at the top: the sprint start date in B3 (Mon Nov 2, 2026), the number of working days in B4 (10), and the committed points in B5. Committed points are all points added on or before the start date:

=SUMIFS(tblStories[Points], tblStories[Added Date], "<="&B3)

In the sample this returns 55. The mid-sprint story is not counted, which is right: the ideal line shows the plan the team committed to.

Step 2: Build the day table with WORKDAY

Below the inputs, make a table with Day 0 to Day 10 in column A. Day 0 is the starting line, so its date is simply the start date. For Day 1 onward, each date is the end of that working day:

=WORKDAY($B$3, A9-1)

WORKDAY skips Saturdays and Sundays, so Day 6 lands on Monday, Nov 9, not on the weekend. If your team has a holiday in the sprint, add a holiday list as the third argument. If your weekend is not Saturday-Sunday, use WORKDAY.INTL instead.

Step 3: Add the ideal line

=$B$5 - $B$5/$B$4*A8

Committed points minus an equal share for each day passed. With 55 points over 10 days, that is 5.5 points a day: 55.0, 49.5, 44.0 and so on down to 0.0 on Day 10.

Step 4: Track scope per day

=SUMIFS(tblStories[Points], tblStories[Added Date], "<="&B9)

This is the column most burndown tutorials skip. It adds up every story that existed on that day. It stays at 55 until Day 4, then jumps to 60 when the payment bug arrives.

Step 5: Calculate actual remaining

First the points completed up to each day (Day 0 is simply 0):

=SUMIFS(tblStories[Points], tblStories[Done Date], "<="&B9)

Then the actual remaining is scope minus completed:

=D8 - E8

Unfinished stories have a blank Done Date, so SUMIFS never counts them as done. That is why the sprint ends at 3 points, not 0.

Burndown chart in Excel day table with ideal remaining, scope, completed and actual remaining columns
The finished day table. Note Day 4: completed goes up, but actual remaining also goes up, from 43 to 45.

Step 6: Insert the line chart and format it

  1. Click inside the day table and go to Insert > Charts > Line with Markers.
  2. Right-click the chart, choose Select Data, and keep only Ideal Remaining and Actual Remaining as series. Set the horizontal axis labels to the Day column.
  3. Format the ideal series: grey, dashed, no markers. Format the actual series: a strong solid colour with round markers.
  4. Set the vertical axis minimum to 0, add the axis titles “Sprint day” and “Points remaining”, and move the legend to the bottom.

Because the chart reads from the Table, it grows when you add rows or change a done date.

How to read this sprint’s burndown

Here is what the Harbor Lane chart tells the team, in plain words:

  • Day 1 is flat at 55. Work started, but nothing was finished. Points only burn when a story is done, so a flat first day is normal. Several flat days in a row is a warning.
  • Day 4 goes up, from 43 to 45. That is the 5-point story added mid-sprint. A burndown line that rises always means new scope, never negative work.
  • Days 5 to 9 run parallel to the ideal line, about 5 to 10 points behind. The team was keeping pace but never caught up after the slow start and the scope change.
  • Day 10 ends at 3. Story S-112 carries over to the next sprint. The team completed 57 points; that number is its velocity for this sprint.
Burndown chart in Excel cheat sheet with 6 steps, 4 formulas and how to read the chart
Save this cheat sheet: the 6 steps and how to read the chart on one page.

Bonus: a burnup chart from the same table

A burndown chart mixes two things into one line: work finished and work added. When scope changes often, a burnup chart is clearer. It plots the Scope column and the Completed column as two separate lines. The gap between them is the work left.

Burnup chart in Excel with the scope line and the completed story points line
Same sprint as a burnup chart: the scope step on Day 4 is easy to see.

You already have both columns, so it takes one more Line chart: select Day, Scope and Completed. Stakeholders who ask “why did the sprint slip?” usually get the answer from this chart in seconds.

4 mistakes to avoid

  1. Counting partly done stories. Burn points only when a story is fully done. Counting 50% of a story makes the chart look good and hides risk.
  2. Using calendar days. A plain date + 1 puts weekends on the axis and the line goes flat every Saturday. Use WORKDAY.
  3. Typing the remaining points by hand. Typed numbers drift from the backlog. Let SUMIFS read the done dates.
  4. Recalculating the ideal line when scope changes. Keep the ideal line on the committed points. The rise in the actual line is the honest signal that scope moved.

Where this fits in the course

In Project Management in Excel, this chart is one lesson in Module 11, after building a product backlog with story points and MoSCoW, sprint planning with capacity, and a Kanban board with dynamic arrays. The same lesson adds the velocity chart. Earlier modules cover the Excel skills behind it (WORKDAY.INTL, SUMIFS and dynamic arrays in Module 2), and Module 12 puts the charts on a one-page sponsor dashboard. If you want the classic side of planning too, my free Gantt chart in Excel tutorial on PK: An Excel Expert is a good next step, and the SUMIFS guide explains the formula that does the heavy lifting here.

NextGenTemplates Academy course

Project Management in Excel: Plan, Schedule, Track & Report

88 lessons in 17 modules (Module 0 to the Module 16 capstone) · 72 video lessons (9h 32m) · 19 practice workbooks · charter, WBS, critical path schedule, four kinds of Gantt chart, resources and RACI, budget and S-curve, earned value (SPI, CPI, EAC), RAID log, Agile backlog, Kanban and burndown charts, sponsor and portfolio dashboards, Google Sheets and Power BI add-on modules · certificate of completion · lifetime access.

Price: ₹3,900 in India (regular ₹5,999) · $79 internationally (regular $119). One-time payment, no subscription. Needs Excel 365 or Excel 2021. No project management background needed. NextGenTemplates is trusted by 10,000+ customers in 180+ countries.

View the course and free preview lessons

Still choosing what to learn? Browse the Academy learning paths, test your Excel skills, or read which Excel skills to put on your resume.

Frequently asked questions

Does Excel have a built-in burndown chart?

No. Excel has no burndown chart type, but a normal Line chart does the job. You build a small table with the ideal and actual remaining work for each day and chart those two columns.

Should a burndown chart use story points or hours?

Either works with the same formulas. Story points are more common in Scrum teams because they burn only when a story is finished. Hours suit teams that log time daily. Pick one and do not mix them in one chart.

Why does my burndown line go up?

Work was added to the sprint. In the sample, a 5-point story added on Day 4 pushed the remaining points from 43 to 45. Track scope in its own column so you can show exactly when and why it happened.

What is the difference between a burndown and a burnup chart?

A burndown chart shows the work left as one falling line. A burnup chart shows total scope and completed work as two separate lines, so scope changes and progress do not hide each other.

Can I make a burndown chart in Google Sheets?

Yes. WORKDAY and SUMIFS work the same way in Google Sheets, and a line chart gives the same result. Use normal ranges instead of Excel Table references.

Next sprint, skip the whiteboard drawing: drop your stories into the practice file and the chart builds itself. Happy planning!